Forthcoming Roadworks in Shepherd's Bush
Where to expect delays and diversions in days ahead
Uxbridge Road
02 June — 04 June
Delays likely - Traffic control (multi-way signals)
Works description : Install 13m of 1 way poly duct in Carriageway,Install 3m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500297077102
|
West Cross Route
02 June — 03 June
Delays likely - Road closure
Works description : Cyclical maintenance Works
Responsibility for works: Transport for London
Current status: Advanced planning
Works reference: YG431461034
|
West Cross Route
03 June — 04 June
Delays likely - Road closure
Works description : Cyclical Maintenance Works
Responsibility for works: Transport for London
Current status: Advanced planning
Works reference: YG431461036
Shepherd's Bush Road
01 June — 04 July
Delays likely - Lane closure
Works description : Connections Projects:Installation of a new electricity supply for a customer:Excavation of trench to ducts for 11kv cables
Responsibility for works: UK POWER NETWORKS EASTERN & LONDON
Current status: Planned work about to start
Works reference: EC40010781675 |
Uxbridge Road, Shepherd's Bush
11 May — 05 June
Delays likely - Traffic control (multi-way signals)
Works description : Excavate within the C/W to complete connection is required between 30" and a 24" cast iron water trunk mains. The connection will serve as a contingency for local supply in case either 30" or 24" mains need to be ioslated in an emergency
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU277HAMCO01 |
A4020 The Vale, Acton
22 April — 03 June
Delays likely - Traffic control (two-way signals)
Works description : CISBOT Internal Mains Sealing long cycle
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000881837
Information supplied by one.network
|